Trying to figure out if we are making progress or not!!
The builders have finished their contract of works, i.e. the full construction, however I have kept them on for a week to really push forward whilst I am on holiday.
We are making headway, slowly.
In the last few days we have finished the living room!!
Built all the partitions in the attic so the staircase is now blocked in, also so is the en suite,
I have completed the first fix electrics in the attic and awaiting them to be check off by the council,
Plastered the en suite in the new bedroom above the garage,
Plaster boarded the ceiling in the bedroom above the garage, (Now ready to be plastered)
Completed the insulation in the attic, what a job, took one guy 3 days, (Being signed off be building control tomorrow, fingers crossed)
Removed the boiler so it can be repositioned in the Utility room,
Began to knock down the wall from the house to the Utility room,
Completed the joists in the Utility room
and finally,
Plaster boarded the new dining room walls, only the ceiling to go next.
Garry & Christine
Wednesday 13 August 2008